Friday, September 10, 2010

The contractor is finishing pavement removal on Pfingsten this week. The contractor will continue to prepare the aggregate base course on Pfingsten this week and into early next week. The contractor is scheduled to start paving the hot-mix asphalt binder course on Pfingsten as early as Monday afternoon or Tuesday morning, which will take an estimated 2 to 3 working days (weather permitting). After the asphalt binder course is paved on Pfingsten, the contractor will start pavement removal on the cul-de-sacs off Pfingsten.

No comments:

Post a Comment