Friday, August 27, 2010

The contractor will be finishing up installing the storm sewer connections to the side streets and cul-de-sacs Monday and Tuesday next week and spend a couple of days doing cleanup work in preparation for pavement removal. Weather permitting, pavement removal should start around the middle of next week. The contractor will start at the north end of the project taking out the pavement along the main stem road of Pfingsten. Once this is complete he will put down the first layer of asphalt and then move to the cul-de-sacs for pavement removal.