Weather permitting, Monday, September 27, 2010, the contractor is scheduled to place the first (of two) lift of asphalt in the cul-de-sacs. All vehicles must be removed from the cul-de-sacs between 7:00 A.M. and 5:00 P.M. Parking is available on Rugen, Lindenwood, Springdale and Knollwood during daytime work hours.
After the cul-de-sac paving is complete, the contractor will begin paving the first (of two) layer of asphalt in the driveways and pouring concrete driveway aprons. Residents with concrete driveway aprons will need to park on the street for 4 or 5 days while the concrete cures. The contractor is scheduled to construct the concrete sidewalk on the east side of Pfingsten mid- to late next week. Residents with sidewalks through their driveways shall also need to park on the street or cul-de-sac for 4 or 5 days also. The contractor will notify residents that need to have their vehicles moved out for concrete work.
All work is weather dependent.
Friday, September 24, 2010
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment