Friday, August 20, 2010
The storm sewer mainline along Pfingsten Road has been completed! The contractor will take a few days completing the storm sewer into the cul-de-sacs. Road removal and preparation should begin the first week of September. This will involve removing the existing roadway and then preparing the base for asphalt. The contractor plans to remove Pfingsten Road first, before doing any of the cul-de-sacs.