Friday, June 4, 2010

The Horizontal Directional Drilling of the water main has been completed. A small section of the 16” water main along Pfingsten has to be completed, and the water main down each cul-de-sac is ongoing.

Water main will need to be installed across Pfingsten at Glenview Road, which will close access in and out of Pfingsten Road. This work will take place in approximately two weeks and will last for 1-2 days. More information will be sent out as we near that date. All traffic will be routed via Betty Lane.