Thursday, October 28, 2010

UPDATE!

Hot-mix asphalt surface course will be paved early next week.

Friday, October 22, 2010

The Contractor is scheduled to continue parkway grading, topsoil and restoration into next week. The final lift of hot-mix asphalt surface is scheduled for next week (weather permitting).

Friday, October 15, 2010

The Contractor is scheduled to continue parkway grading and utility structure adjustments into next week. Topsoil and restoration is scheduled for next week. The final lift of hot-mix asphalt surface is scheduled for later this month.

Friday, October 8, 2010

The first lift of asphalt (hot-mix asphalt binder course) is complete for Pfingsten Road and the cul-de-sacs. The sidewalk along the east side of Pfingsten is complete. The Contractor is scheduled to continue driveway replacement and parkway grading into next week.

Friday, October 1, 2010

The first lift of asphalt (hot-mix asphalt binder course) is complete for Pfingsten Road and the cul-de-sacs.

The contractor is scheduled to continue construction of the sidewalk along the east side of Pfingsten Road and grading ditches and parkways.